Digital Train Radio System (DTRS) Obsolescence Upgrades Program (PTV) appears in 3 snapshots of the Victorian IT dashboard, from 2016-17 Q3 to 2017-18 Q1.
Its cost is $17m at 2017-18 Q1, against $16m at its baseline: +1%.
Its planned finish is 10 Dec 2018, 1 months later than the 10 Nov 2018 first planned.
Its latest rating is Green (2017-18 Q1).