Victorian Transport Digital Engineering Transformation Program (DTP) appears in 10 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2025-26 Q2.
Its cost is $45m at 2025-26 Q2, against $5.1m at its baseline: +776%.
Its planned finish is 30 Jun 2026, 30 months later than the 29 Dec 2023 first planned.
Its latest rating is Amber (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Victorian Transport Digital Engineering Transformation Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpvictoriantransportdigitalengineeringtransformationprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Victorian Transport Digital Engineering Transformation Program cost? Its cost is $45m at 2025-26 Q2, against $5.1m at its baseline: +776%.
Is Victorian Transport Digital Engineering Transformation Program late? Its planned finish is 30 Jun 2026, 30 months later than the 29 Dec 2023 first planned.
What is Victorian Transport Digital Engineering Transformation Program's latest rating? Its latest rating is Amber (2025-26 Q2).