VGV Going Digital Project (DTP) appears in one Victorian IT dashboard snapshot, 2022-23 Q3.
Its cost is $2.6m at 2022-23 Q3, against $0.5m at its baseline: +408%.
Its planned finish is 30 Mar 2023, 42 months later than the 30 Sep 2019 first planned.
Its latest rating is Green (2022-23 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VGV Going Digital Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpvgvgoingdigitalproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does VGV Going Digital Project cost? Its cost is $2.6m at 2022-23 Q3, against $0.5m at its baseline: +408%.
Is VGV Going Digital Project late? Its planned finish is 30 Mar 2023, 42 months later than the 30 Sep 2019 first planned.
What is VGV Going Digital Project's latest rating? Its latest rating is Green (2022-23 Q3).