Speed Change Management Tool Project (DTP) appears in 10 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q4.
Its planned finish is 30 Jun 2025, 11 months later than the 31 Jul 2024 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Speed Change Management Tool Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpspeedchangemanagementtoolproject, as at 18 May 2026. Licence: CC BY 4.0.
Is Speed Change Management Tool Project late? Its planned finish is 30 Jun 2025, 11 months later than the 31 Jul 2024 first planned.
What is Speed Change Management Tool Project's latest rating? Its latest rating is Green (2024-25 Q4).