Smarter Roads Program - Timetable Systems Uplift (DTP) appears in 12 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2025-26 Q2.
Its cost is $6.7m at 2025-26 Q2, against $4.7m at its baseline: +42%.
Its planned finish is 31 Mar 2026, 36 months later than the 31 Mar 2023 first planned.
Its latest rating is Amber (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Smarter Roads Program - Timetable Systems Uplift. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpsmarterroadsprogramtimetablesystemsuplift, as at 18 May 2026. Licence: CC BY 4.0.
How much does Smarter Roads Program - Timetable Systems Uplift cost? Its cost is $6.7m at 2025-26 Q2, against $4.7m at its baseline: +42%.
Is Smarter Roads Program - Timetable Systems Uplift late? Its planned finish is 31 Mar 2026, 36 months later than the 31 Mar 2023 first planned.
What is Smarter Roads Program - Timetable Systems Uplift's latest rating? Its latest rating is Amber (2025-26 Q2).