OneDigital Workplace (DTP) appears in 6 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2025-26 Q2.
Its cost is $10m at 2025-26 Q2, against $10m at its baseline: +0%.
Its planned finish is 30 Dec 2026, 6 months later than the 30 Jun 2026 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: OneDigital Workplace. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtponedigitalworkplace, as at 18 May 2026. Licence: CC BY 4.0.
How much does OneDigital Workplace cost? Its cost is $10m at 2025-26 Q2, against $10m at its baseline: +0%.
Is OneDigital Workplace late? Its planned finish is 30 Dec 2026, 6 months later than the 30 Jun 2026 first planned.
What is OneDigital Workplace's latest rating? Its latest rating is Green (2025-26 Q2).