MOG 2023- Finance and Procurement System Stream (DTP) appears in 6 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2024-25 Q2.
Its cost is $3.8m at 2024-25 Q2, against $2.3m at its baseline: +66%.
Its planned finish is 30 Dec 2024, 3 months later than the 30 Sep 2024 first planned.
Its latest rating is Green (2024-25 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: MOG 2023- Finance and Procurement System Stream. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpmog2023financeandprocurementsystemstream, as at 18 May 2026. Licence: CC BY 4.0.
How much does MOG 2023- Finance and Procurement System Stream cost? Its cost is $3.8m at 2024-25 Q2, against $2.3m at its baseline: +66%.
Is MOG 2023- Finance and Procurement System Stream late? Its planned finish is 30 Dec 2024, 3 months later than the 30 Sep 2024 first planned.
What is MOG 2023- Finance and Procurement System Stream's latest rating? Its latest rating is Green (2024-25 Q2).