Human Capital Management (HCM) Project - Phase 2 (DTP) appears in 10 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2025-26 Q2.
Its cost is $14m at 2025-26 Q2, against $7.5m at its baseline: +82%.
Its planned finish is 31 Dec 2025, 18 months later than the 30 Jun 2024 first planned.
Its latest rating is Amber (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Human Capital Management (HCM) Project - Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtphumancapitalmanagementhcmprojectphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Human Capital Management (HCM) Project - Phase 2 cost? Its cost is $14m at 2025-26 Q2, against $7.5m at its baseline: +82%.
Is Human Capital Management (HCM) Project - Phase 2 late? Its planned finish is 31 Dec 2025, 18 months later than the 30 Jun 2024 first planned.
What is Human Capital Management (HCM) Project - Phase 2's latest rating? Its latest rating is Amber (2025-26 Q2).