Heavy Vehicle - Structural Assessment and Permit System (HV-SAPS) (DTP) appears in 10 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q4.
Its planned finish is 3 Apr 2025, 6 months later than the 20 Sep 2024 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Heavy Vehicle - Structural Assessment and Permit System (HV-SAPS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpheavyvehiclestructuralassessmentandpermitsystemhvsaps, as at 18 May 2026. Licence: CC BY 4.0.
Is Heavy Vehicle - Structural Assessment and Permit System (HV-SAPS) late? Its planned finish is 3 Apr 2025, 6 months later than the 20 Sep 2024 first planned.
What is Heavy Vehicle - Structural Assessment and Permit System (HV-SAPS)'s latest rating? Its latest rating is Green (2024-25 Q4).