Future Public Transport Ticketing System (DTP) appears in 10 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2025-26 Q2.
Its cost is $680m at 2025-26 Q2, against $543m at its baseline: +25%.
Its planned finish is 31 Dec 2028, 6 months later than the 30 Jun 2028 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Future Public Transport Ticketing System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dtpfuturepublictransportticketingsystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Future Public Transport Ticketing System cost? Its cost is $680m at 2025-26 Q2, against $543m at its baseline: +25%.
Is Future Public Transport Ticketing System late? Its planned finish is 31 Dec 2028, 6 months later than the 30 Jun 2028 first planned.
What is Future Public Transport Ticketing System's latest rating? Its latest rating is Green (2025-26 Q2).