Emergency Management Victoria-VCDI Partnership (DPC) appears in 8 snapshots of the Victorian IT dashboard, from 2020-21 Q3 to 2022-23 Q2.
Its planned finish is 28 Feb 2023, 8 months later than the 30 Jun 2022 first planned.
Its latest rating is Green (2022-23 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Emergency Management Victoria-VCDI Partnership. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dpcemergencymanagementvictoriavcdipartnership, as at 18 May 2026. Licence: CC BY 4.0.
Is Emergency Management Victoria-VCDI Partnership late? Its planned finish is 28 Feb 2023, 8 months later than the 30 Jun 2022 first planned.
What is Emergency Management Victoria-VCDI Partnership's latest rating? Its latest rating is Green (2022-23 Q2).