DPC - Digital Office Upgrade Project (DPC) appears in 5 snapshots of the Victorian IT dashboard, from 2018-19 Q1 to 2019-20 Q1.
Its cost is $2.3m at 2019-20 Q1, against $2.3m at its baseline: +1%.
Its planned finish is 30 Aug 2019, 5 months later than the 29 Mar 2019 first planned.
Its latest rating is Green (2019-20 Q1), up from Amber at 2018-19 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: DPC - Digital Office Upgrade Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dpcdpcdigitalofficeupgradeproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does DPC - Digital Office Upgrade Project cost? Its cost is $2.3m at 2019-20 Q1, against $2.3m at its baseline: +1%.
Is DPC - Digital Office Upgrade Project late? Its planned finish is 30 Aug 2019, 5 months later than the 29 Mar 2019 first planned.
What is DPC - Digital Office Upgrade Project's latest rating? Its latest rating is Green (2019-20 Q1), up from Amber at 2018-19 Q1.