Smarter Roads Program - Open Data (DOT) appears in 6 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2022-23 Q2.
Its cost is $5.4m at 2022-23 Q2, against $2.1m at its baseline: +161%.
Its planned finish is 30 Jun 2023, 12 months later than the 30 Jun 2022 first planned.
Its latest rating is Amber (2022-23 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Smarter Roads Program - Open Data. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dotsmarterroadsprogramopendata, as at 18 May 2026. Licence: CC BY 4.0.
How much does Smarter Roads Program - Open Data cost? Its cost is $5.4m at 2022-23 Q2, against $2.1m at its baseline: +161%.
Is Smarter Roads Program - Open Data late? Its planned finish is 30 Jun 2023, 12 months later than the 30 Jun 2022 first planned.
What is Smarter Roads Program - Open Data's latest rating? Its latest rating is Amber (2022-23 Q2).