Registration and Licence Data Quality Project -Stage 2 (DOT) appears in 7 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2020-21 Q3.
Its cost is $5.2m at 2020-21 Q3, against $5.2m at its baseline: -1%.
Its planned finish is 31 Mar 2021, 4 months later than the 20 Nov 2020 first planned.
Its latest rating is Green (2020-21 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Registration and Licence Data Quality Project -Stage 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dotregistrationandlicencedataqualityprojectstage2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Registration and Licence Data Quality Project -Stage 2 cost? Its cost is $5.2m at 2020-21 Q3, against $5.2m at its baseline: -1%.
Is Registration and Licence Data Quality Project -Stage 2 late? Its planned finish is 31 Mar 2021, 4 months later than the 20 Nov 2020 first planned.
What is Registration and Licence Data Quality Project -Stage 2's latest rating? Its latest rating is Green (2020-21 Q3).