Oracle Cloud Project (DOT) appears in 8 snapshots of the Victorian IT dashboard, from 2019-20 Q2 to 2021-22 Q1.
Its cost is $39m at 2021-22 Q1, against $30m at its baseline: +33%.
Its planned finish is 31 Aug 2021, 5 months later than the 31 Mar 2021 first planned.
Its latest rating is Green (2021-22 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Oracle Cloud Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dotoraclecloudproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Oracle Cloud Project cost? Its cost is $39m at 2021-22 Q1, against $30m at its baseline: +33%.
Is Oracle Cloud Project late? Its planned finish is 31 Aug 2021, 5 months later than the 31 Mar 2021 first planned.
What is Oracle Cloud Project's latest rating? Its latest rating is Green (2021-22 Q1).