myki and PTV Website Integration and Development (DOT) appears in 6 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2020-21 Q2.
Its cost is $8.0m at 2020-21 Q2, against $3.6m at its baseline: +119%.
Its planned finish is 30 Oct 2020, 36 months later than the 8 Nov 2017 first planned.
Its latest rating is Green (2020-21 Q2), up from Amber at 2019-20 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: myki and PTV Website Integration and Development. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dotmykiandptvwebsiteintegrationanddevelopment, as at 18 May 2026. Licence: CC BY 4.0.
How much does myki and PTV Website Integration and Development cost? Its cost is $8.0m at 2020-21 Q2, against $3.6m at its baseline: +119%.
Is myki and PTV Website Integration and Development late? Its planned finish is 30 Oct 2020, 36 months later than the 8 Nov 2017 first planned.
What is myki and PTV Website Integration and Development's latest rating? Its latest rating is Green (2020-21 Q2), up from Amber at 2019-20 Q1.