DoT Integration: Identity and Access Join (DOT) appears in 6 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2022-23 Q2.
Its planned finish is 31 Mar 2023, 12 months later than the 25 Mar 2022 first planned.
Its latest rating is Amber (2022-23 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: DoT Integration: Identity and Access Join. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dotdotintegrationidentityandaccessjoin, as at 18 May 2026. Licence: CC BY 4.0.
Is DoT Integration: Identity and Access Join late? Its planned finish is 31 Mar 2023, 12 months later than the 25 Mar 2022 first planned.
What is DoT Integration: Identity and Access Join's latest rating? Its latest rating is Amber (2022-23 Q2).