Connect System Upgrade (DOT) appears in 4 snapshots of the Victorian IT dashboard, from 2020-21 Q1 to 2020-21 Q4.
Its planned finish is 30 Jun 2021, 3 months later than the 31 Mar 2021 first planned.
Its latest rating is Green (2020-21 Q4), up from Amber at 2020-21 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Connect System Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dotconnectsystemupgrade, as at 18 May 2026. Licence: CC BY 4.0.
Is Connect System Upgrade late? Its planned finish is 30 Jun 2021, 3 months later than the 31 Mar 2021 first planned.
What is Connect System Upgrade's latest rating? Its latest rating is Green (2020-21 Q4), up from Amber at 2020-21 Q1.