Machinery of Government (MOG) changes - IT component (DJSIR) appears in 3 snapshots of the Victorian IT dashboard, from 2023-24 Q3 to 2024-25 Q1.
Its cost is $1.2m at 2024-25 Q1, against $1.5m at its baseline: -19%.
Its planned finish is 31 Aug 2024, 2 months later than the 30 Jun 2024 first planned.
Its latest rating is Green (2024-25 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Machinery of Government (MOG) changes - IT component. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djsirmachineryofgovernmentmogchangesitcomponent, as at 18 May 2026. Licence: CC BY 4.0.
How much does Machinery of Government (MOG) changes - IT component cost? Its cost is $1.2m at 2024-25 Q1, against $1.5m at its baseline: -19%.
Is Machinery of Government (MOG) changes - IT component late? Its planned finish is 31 Aug 2024, 2 months later than the 30 Jun 2024 first planned.
What is Machinery of Government (MOG) changes - IT component's latest rating? Its latest rating is Green (2024-25 Q1).