Rostering for Prisons (DJR) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $5.4m at 2017-18 Q2, against $1.4m at its baseline: +288%.
Its planned finish is 15 Dec 2017, 30 months later than the 30 Jun 2015 first planned.
Its latest rating is Green (2017-18 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Rostering for Prisons. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djrrosteringforprisons, as at 18 May 2026. Licence: CC BY 4.0.
How much does Rostering for Prisons cost? Its cost is $5.4m at 2017-18 Q2, against $1.4m at its baseline: +288%.
Is Rostering for Prisons late? Its planned finish is 15 Dec 2017, 30 months later than the 30 Jun 2015 first planned.
What is Rostering for Prisons's latest rating? Its latest rating is Green (2017-18 Q2).