Prisoner Transport Order System (PTOS) (DJR) appears in 5 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q2.
Its cost is $7.5m at 2018-19 Q2, against $3.8m at its baseline: +100%.
Its planned finish is 31 Jan 2019, 29 months later than the 5 Sep 2016 first planned.
Its latest rating is Green (2018-19 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Prisoner Transport Order System (PTOS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djrprisonertransportordersystemptos, as at 18 May 2026. Licence: CC BY 4.0.
How much does Prisoner Transport Order System (PTOS) cost? Its cost is $7.5m at 2018-19 Q2, against $3.8m at its baseline: +100%.
Is Prisoner Transport Order System (PTOS) late? Its planned finish is 31 Jan 2019, 29 months later than the 5 Sep 2016 first planned.
What is Prisoner Transport Order System (PTOS)'s latest rating? Its latest rating is Green (2018-19 Q2).