Oracle R12 & BI Implementation Project (DJR) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $5.1m at 2017-18 Q2, against $4.1m at its baseline: +24%.
Its planned finish is 8 Nov 2017, 4 months later than the 1 Jul 2017 first planned.
Its latest rating is Green (2017-18 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Oracle R12 & BI Implementation Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djroracler12biimplementationproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Oracle R12 & BI Implementation Project cost? Its cost is $5.1m at 2017-18 Q2, against $4.1m at its baseline: +24%.
Is Oracle R12 & BI Implementation Project late? Its planned finish is 8 Nov 2017, 4 months later than the 1 Jul 2017 first planned.
What is Oracle R12 & BI Implementation Project's latest rating? Its latest rating is Green (2017-18 Q2).