Justice eProcurement Implementation (JEPI) Project (DJR) appears in 4 snapshots of the Victorian IT dashboard, from 2017-18 Q3 to 2018-19 Q2.
Its planned finish is 12 Apr 2019, 5 months later than the 12 Nov 2018 first planned.
Its latest rating is Green (2018-19 Q2), up from Amber at 2017-18 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Justice eProcurement Implementation (JEPI) Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djrjusticeeprocurementimplementationjepiproject, as at 18 May 2026. Licence: CC BY 4.0.
Is Justice eProcurement Implementation (JEPI) Project late? Its planned finish is 12 Apr 2019, 5 months later than the 12 Nov 2018 first planned.
What is Justice eProcurement Implementation (JEPI) Project's latest rating? Its latest rating is Green (2018-19 Q2), up from Amber at 2017-18 Q3.