Electronic Sourcing Project (DJR) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $1.1m at 2017-18 Q2, against $3.0m at its baseline: -63%.
Its planned finish is 31 Oct 2017, 2 months later than the 31 Aug 2017 first planned.
Its latest rating is Green (2017-18 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Electronic Sourcing Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djrelectronicsourcingproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Electronic Sourcing Project cost? Its cost is $1.1m at 2017-18 Q2, against $3.0m at its baseline: -63%.
Is Electronic Sourcing Project late? Its planned finish is 31 Oct 2017, 2 months later than the 31 Aug 2017 first planned.
What is Electronic Sourcing Project's latest rating? Its latest rating is Green (2017-18 Q2).