E*Justice Strengthened Enforcement (DJR) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $1.9m at 2017-18 Q2, against $1.0m at its baseline: +82%.
Its planned finish is 3 Oct 2017, 15 months later than the 30 Jun 2016 first planned.
Its latest rating is Green (2017-18 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: E*Justice Strengthened Enforcement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djrejusticestrengthenedenforcement, as at 18 May 2026. Licence: CC BY 4.0.
How much does E*Justice Strengthened Enforcement cost? Its cost is $1.9m at 2017-18 Q2, against $1.0m at its baseline: +82%.
Is E*Justice Strengthened Enforcement late? Its planned finish is 3 Oct 2017, 15 months later than the 30 Jun 2016 first planned.
What is E*Justice Strengthened Enforcement's latest rating? Its latest rating is Green (2017-18 Q2).