Resources Management System Victoria (RMSVIC) Project (DJPR) appears in 12 snapshots of the Victorian IT dashboard, from 2019-20 Q3 to 2022-23 Q2.
Its cost is $5.2m at 2022-23 Q2, against $5.9m at its baseline: -13%.
Its planned finish is 31 Mar 2023, 15 months later than the 31 Dec 2021 first planned.
Its latest rating is Red (2022-23 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Resources Management System Victoria (RMSVIC) Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djprresourcesmanagementsystemvictoriarmsvicproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Resources Management System Victoria (RMSVIC) Project cost? Its cost is $5.2m at 2022-23 Q2, against $5.9m at its baseline: -13%.
Is Resources Management System Victoria (RMSVIC) Project late? Its planned finish is 31 Mar 2023, 15 months later than the 31 Dec 2021 first planned.
What is Resources Management System Victoria (RMSVIC) Project's latest rating? Its latest rating is Red (2022-23 Q2).