Implementation of Service Management Platform - Phase 2 (DJPR) appears in 7 snapshots of the Victorian IT dashboard, from 2019-20 Q3 to 2021-22 Q1.
Its cost is $1.8m at 2021-22 Q1, against $1.4m at its baseline: +26%.
Its planned finish is 30 Aug 2021, 7 months later than the 3 Feb 2021 first planned.
Its latest rating is Green (2021-22 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Implementation of Service Management Platform - Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djprimplementationofservicemanagementplatformphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Implementation of Service Management Platform - Phase 2 cost? Its cost is $1.8m at 2021-22 Q1, against $1.4m at its baseline: +26%.
Is Implementation of Service Management Platform - Phase 2 late? Its planned finish is 30 Aug 2021, 7 months later than the 3 Feb 2021 first planned.
What is Implementation of Service Management Platform - Phase 2's latest rating? Its latest rating is Green (2021-22 Q1).