GEMS Grants Transformation Project (DJPR) appears in 2 snapshots of the Victorian IT dashboard, from 2019-20 Q2 to 2019-20 Q3.
Its planned finish is 28 Mar 2020, 3 months earlier than the 30 Jun 2020 first planned.
Its latest rating is Green (2019-20 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: GEMS Grants Transformation Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djprgemsgrantstransformationproject, as at 18 May 2026. Licence: CC BY 4.0.
Is GEMS Grants Transformation Project late? Its planned finish is 28 Mar 2020, 3 months earlier than the 30 Jun 2020 first planned.
What is GEMS Grants Transformation Project's latest rating? Its latest rating is Green (2019-20 Q3).