Future Workplace Program (FWP) (DJPR) appears in 4 snapshots of the Victorian IT dashboard, from 2018-19 Q3 to 2019-20 Q2.
Its cost is $15m at 2019-20 Q2, against $10m at its baseline: +54%.
Its planned finish is 30 Nov 2019, 5 months later than the 30 Jun 2019 first planned.
Its latest rating is Green (2019-20 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Future Workplace Program (FWP). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djprfutureworkplaceprogramfwp, as at 18 May 2026. Licence: CC BY 4.0.
How much does Future Workplace Program (FWP) cost? Its cost is $15m at 2019-20 Q2, against $10m at its baseline: +54%.
Is Future Workplace Program (FWP) late? Its planned finish is 30 Nov 2019, 5 months later than the 30 Jun 2019 first planned.
What is Future Workplace Program (FWP)'s latest rating? Its latest rating is Green (2019-20 Q2).