Sentence Calculation and Warrant Administration Digitisation Project (DJCS) appears in 2 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2019-20 Q2.
Its cost is $4.5m at 2019-20 Q2, against $4.2m at its baseline: +6%.
Its planned finish is 30 Sep 2019, 18 months later than the 20 Mar 2018 first planned.
Its latest rating is Green (2019-20 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Sentence Calculation and Warrant Administration Digitisation Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcssentencecalculationandwarrantadministrationdigitisationproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Sentence Calculation and Warrant Administration Digitisation Project cost? Its cost is $4.5m at 2019-20 Q2, against $4.2m at its baseline: +6%.
Is Sentence Calculation and Warrant Administration Digitisation Project late? Its planned finish is 30 Sep 2019, 18 months later than the 20 Mar 2018 first planned.
What is Sentence Calculation and Warrant Administration Digitisation Project's latest rating? Its latest rating is Green (2019-20 Q2).