Road Safety Package (DJCS) appears in 22 snapshots of the Victorian IT dashboard, from 2019-20 Q4 to 2025-26 Q1.
Its cost is $14m at 2025-26 Q1, against $7.0m at its baseline: +95%.
Its planned finish is 23 Jul 2025, 39 months later than the 21 Apr 2022 first planned.
Its latest rating is Green (2025-26 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Road Safety Package. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsroadsafetypackage, as at 18 May 2026. Licence: CC BY 4.0.
How much does Road Safety Package cost? Its cost is $14m at 2025-26 Q1, against $7.0m at its baseline: +95%.
Is Road Safety Package late? Its planned finish is 23 Jul 2025, 39 months later than the 21 Apr 2022 first planned.
What is Road Safety Package's latest rating? Its latest rating is Green (2025-26 Q1).