Provision of a Claim Management Solution (CMS) (DJCS) appears in 4 snapshots of the Victorian IT dashboard, from 2022-23 Q2 to 2023-24 Q1.
Its cost is $1.5m at 2023-24 Q1, against $0.9m at its baseline: +62%.
Its planned finish is 4 Aug 2023, 4 months later than the 30 Mar 2023 first planned.
Its latest rating is Green (2023-24 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Provision of a Claim Management Solution (CMS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsprovisionofaclaimmanagementsolutioncms, as at 18 May 2026. Licence: CC BY 4.0.
How much does Provision of a Claim Management Solution (CMS) cost? Its cost is $1.5m at 2023-24 Q1, against $0.9m at its baseline: +62%.
Is Provision of a Claim Management Solution (CMS) late? Its planned finish is 4 Aug 2023, 4 months later than the 30 Mar 2023 first planned.
What is Provision of a Claim Management Solution (CMS)'s latest rating? Its latest rating is Green (2023-24 Q1).