Prison Industries Enhancement Phase 3 Project (PIE3) (DJCS) appears in 10 snapshots of the Victorian IT dashboard, from 2021-22 Q4 to 2024-25 Q1.
Its cost is $2.9m at 2024-25 Q1, against $2.0m at its baseline: +50%.
Its planned finish is 31 Jul 2024, 1 months later than the 30 Jun 2024 first planned.
Its latest rating is Green (2024-25 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Prison Industries Enhancement Phase 3 Project (PIE3). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsprisonindustriesenhancementphase3projectpie3, as at 18 May 2026. Licence: CC BY 4.0.
How much does Prison Industries Enhancement Phase 3 Project (PIE3) cost? Its cost is $2.9m at 2024-25 Q1, against $2.0m at its baseline: +50%.
Is Prison Industries Enhancement Phase 3 Project (PIE3) late? Its planned finish is 31 Jul 2024, 1 months later than the 30 Jun 2024 first planned.
What is Prison Industries Enhancement Phase 3 Project (PIE3)'s latest rating? Its latest rating is Green (2024-25 Q1).