Prisoner Transport Order System (PTOS) (DJCS) appears in 2 snapshots of the Victorian IT dashboard, from 2018-19 Q3 to 2018-19 Q4.
Its cost is $7.5m at 2018-19 Q4, against $3.8m at its baseline: +100%.
Its planned finish is 30 Apr 2019, 32 months later than the 5 Sep 2016 first planned.
Its latest rating is Green (2018-19 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Prisoner Transport Order System (PTOS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsprisonertransportordersystemptos, as at 18 May 2026. Licence: CC BY 4.0.
How much does Prisoner Transport Order System (PTOS) cost? Its cost is $7.5m at 2018-19 Q4, against $3.8m at its baseline: +100%.
Is Prisoner Transport Order System (PTOS) late? Its planned finish is 30 Apr 2019, 32 months later than the 5 Sep 2016 first planned.
What is Prisoner Transport Order System (PTOS)'s latest rating? Its latest rating is Green (2018-19 Q4).