Practice Management System (DJCS) appears in 18 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2023-24 Q2.
Its cost is $1.5m at 2023-24 Q2, against $1.4m at its baseline: +10%.
Its planned finish is 31 Dec 2023, 33 months later than the 1 Apr 2021 first planned.
Its latest rating is Green (2023-24 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Practice Management System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcspracticemanagementsystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Practice Management System cost? Its cost is $1.5m at 2023-24 Q2, against $1.4m at its baseline: +10%.
Is Practice Management System late? Its planned finish is 31 Dec 2023, 33 months later than the 1 Apr 2021 first planned.
What is Practice Management System's latest rating? Its latest rating is Green (2023-24 Q2).