Mobile Camera Replacement (MCR) Project (DJCS) appears in 6 snapshots of the Victorian IT dashboard, from 2018-19 Q3 to 2019-20 Q4.
Its cost is $16m at 2019-20 Q4, against $2.8m at its baseline: +467%.
Its planned finish is 26 Jun 2020, 54 months later than the 21 Dec 2015 first planned.
Its latest rating is Green (2019-20 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Mobile Camera Replacement (MCR) Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsmobilecamerareplacementmcrproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Mobile Camera Replacement (MCR) Project cost? Its cost is $16m at 2019-20 Q4, against $2.8m at its baseline: +467%.
Is Mobile Camera Replacement (MCR) Project late? Its planned finish is 26 Jun 2020, 54 months later than the 21 Dec 2015 first planned.
What is Mobile Camera Replacement (MCR) Project's latest rating? Its latest rating is Green (2019-20 Q4).