Melbourne Assessment Prison CCTV upgrade (DJCS) appears in 3 snapshots of the Victorian IT dashboard, from 2019-20 Q2 to 2019-20 Q4.
Its cost is $8.9m at 2019-20 Q4, against $4.0m at its baseline: +123%.
Its planned finish is 30 Jun 2020, 45 months later than the 14 Oct 2016 first planned.
Its latest rating is Green (2019-20 Q4), up from Red at 2019-20 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Melbourne Assessment Prison CCTV upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsmelbourneassessmentprisoncctvupgrade, as at 18 May 2026. Licence: CC BY 4.0.
How much does Melbourne Assessment Prison CCTV upgrade cost? Its cost is $8.9m at 2019-20 Q4, against $4.0m at its baseline: +123%.
Is Melbourne Assessment Prison CCTV upgrade late? Its planned finish is 30 Jun 2020, 45 months later than the 14 Oct 2016 first planned.
What is Melbourne Assessment Prison CCTV upgrade's latest rating? Its latest rating is Green (2019-20 Q4), up from Red at 2019-20 Q2.