Industries Engagement and Enforcement Project (DJCS) appears in 2 snapshots of the Victorian IT dashboard, from 2021-22 Q3 to 2021-22 Q4.
Its cost is $14m at 2021-22 Q4, against $7.0m at its baseline: +107%.
Its planned finish is 30 Jun 2022, 7 months later than the 30 Nov 2021 first planned.
Its latest rating is Green (2021-22 Q4).
The source marks it completed.