Identity and Access Management (IDAM) PHASE 2 (DJCS) appears in 8 snapshots of the Victorian IT dashboard, from 2021-22 Q4 to 2023-24 Q3.
Its cost is $1.3m at 2023-24 Q3, against $0.9m at its baseline: +38%.
Its planned finish is 30 Jan 2024, 18 months later than the 31 Jul 2022 first planned.
Its latest rating is Green (2023-24 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Identity and Access Management (IDAM) PHASE 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsidentityandaccessmanagementidamphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Identity and Access Management (IDAM) PHASE 2 cost? Its cost is $1.3m at 2023-24 Q3, against $0.9m at its baseline: +38%.
Is Identity and Access Management (IDAM) PHASE 2 late? Its planned finish is 30 Jan 2024, 18 months later than the 31 Jul 2022 first planned.
What is Identity and Access Management (IDAM) PHASE 2's latest rating? Its latest rating is Green (2023-24 Q3).