Emergency Alert Phase 4 - Delivery (DJCS) appears in 11 snapshots of the Victorian IT dashboard, from 2018-19 Q3 to 2021-22 Q1.
Its cost is $18m at 2021-22 Q1, against $7.6m at its baseline: +137%.
Its planned finish is 1 Sep 2021, 14 months later than the 30 Jun 2020 first planned.
Its latest rating is Green (2021-22 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Emergency Alert Phase 4 - Delivery. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsemergencyalertphase4delivery, as at 18 May 2026. Licence: CC BY 4.0.
How much does Emergency Alert Phase 4 - Delivery cost? Its cost is $18m at 2021-22 Q1, against $7.6m at its baseline: +137%.
Is Emergency Alert Phase 4 - Delivery late? Its planned finish is 1 Sep 2021, 14 months later than the 30 Jun 2020 first planned.
What is Emergency Alert Phase 4 - Delivery's latest rating? Its latest rating is Green (2021-22 Q1).