Digital Radio Upgrade Program - Stage 2 (DJCS) appears in 26 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2025-26 Q2.
Its cost is $118m at 2025-26 Q2, against $70m at its baseline: +67%.
Its planned finish is 30 Jun 2026, 36 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Digital Radio Upgrade Program - Stage 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/djcsdigitalradioupgradeprogramstage2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Digital Radio Upgrade Program - Stage 2 cost? Its cost is $118m at 2025-26 Q2, against $70m at its baseline: +67%.
Is Digital Radio Upgrade Program - Stage 2 late? Its planned finish is 30 Jun 2026, 36 months later than the 30 Jun 2023 first planned.
What is Digital Radio Upgrade Program - Stage 2's latest rating? Its latest rating is Green (2025-26 Q2).