VAHI Information Management Environment (VIME) and Portal - Phase 2 (DH) appears in 2 snapshots of the Victorian IT dashboard, from 2020-21 Q3 to 2020-21 Q4.
Its cost is $8.6m at 2020-21 Q4, against $7.8m at its baseline: +9%.
Its planned finish is 30 Jun 2021, 6 months earlier than the 31 Dec 2021 first planned.
Its latest rating is Green (2020-21 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VAHI Information Management Environment (VIME) and Portal - Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhvahiinformationmanagementenvironmentvimeandportalphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does VAHI Information Management Environment (VIME) and Portal - Phase 2 cost? Its cost is $8.6m at 2020-21 Q4, against $7.8m at its baseline: +9%.
Is VAHI Information Management Environment (VIME) and Portal - Phase 2 late? Its planned finish is 30 Jun 2021, 6 months earlier than the 31 Dec 2021 first planned.
What is VAHI Information Management Environment (VIME) and Portal - Phase 2's latest rating? Its latest rating is Green (2020-21 Q4).