Our Briefings Phase 2 (DH) appears in 2 snapshots of the Victorian IT dashboard, from 2020-21 Q3 to 2020-21 Q4.
Its cost is $2.2m at 2020-21 Q4, against $2.1m at its baseline: +8%.
Its planned finish is 30 Jun 2021, 5 months later than the 2 Feb 2021 first planned.
Its latest rating is Green (2020-21 Q4).
The source marks it completed.