Orygen ICT Transition Project (DH) appears in 5 snapshots of the Victorian IT dashboard, from 2022-23 Q4 to 2023-24 Q4.
Its planned finish is 28 Jun 2024, 2 months later than the 30 Apr 2024 first planned.
Its latest rating is Red (2023-24 Q4).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Orygen ICT Transition Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhorygenicttransitionproject, as at 18 May 2026. Licence: CC BY 4.0.
Is Orygen ICT Transition Project late? Its planned finish is 28 Jun 2024, 2 months later than the 30 Apr 2024 first planned.
What is Orygen ICT Transition Project's latest rating? Its latest rating is Red (2023-24 Q4).