Infrastructure Resilience (DH) appears in 2 snapshots of the Victorian IT dashboard, from 2020-21 Q3 to 2020-21 Q4.
Its cost is $4.3m at 2020-21 Q4, against $1.8m at its baseline: +135%.
Its planned finish is 30 Jun 2021, 24 months later than the 30 Jun 2019 first planned.
Its latest rating is Red (2020-21 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Infrastructure Resilience. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhinfrastructureresilience, as at 18 May 2026. Licence: CC BY 4.0.
How much does Infrastructure Resilience cost? Its cost is $4.3m at 2020-21 Q4, against $1.8m at its baseline: +135%.
Is Infrastructure Resilience late? Its planned finish is 30 Jun 2021, 24 months later than the 30 Jun 2019 first planned.
What is Infrastructure Resilience's latest rating? Its latest rating is Red (2020-21 Q4).