Human Capital Management System (DH) appears in 4 snapshots of the Victorian IT dashboard, from 2020-21 Q3 to 2021-22 Q2.
Its cost is $14m at 2021-22 Q2, against $9.0m at its baseline: +54%.
Its planned finish is 30 Nov 2021, 17 months later than the 30 Jun 2020 first planned.
Its latest rating is Green (2021-22 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Human Capital Management System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhhumancapitalmanagementsystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Human Capital Management System cost? Its cost is $14m at 2021-22 Q2, against $9.0m at its baseline: +54%.
Is Human Capital Management System late? Its planned finish is 30 Nov 2021, 17 months later than the 30 Jun 2020 first planned.
What is Human Capital Management System's latest rating? Its latest rating is Green (2021-22 Q2).