Infrastructure Resilience (DHHS) appears in 10 snapshots of the Victorian IT dashboard, from 2018-19 Q1 to 2020-21 Q2.
Its cost is $4.9m at 2020-21 Q2, against $1.8m at its baseline: +169%.
Its planned finish is 31 Mar 2021, 21 months later than the 30 Jun 2019 first planned.
Its latest rating is Red (2020-21 Q2), down from Green at 2018-19 Q1.