ICT Fit out of Orange Door Sites (DHHS) appears in 6 snapshots of the Victorian IT dashboard, from 2018-19 Q1 to 2019-20 Q2.
Its planned finish is 31 Oct 2019, 10 months later than the 31 Dec 2018 first planned.
Its latest rating is Green (2019-20 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: ICT Fit out of Orange Door Sites. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhhsictfitoutoforangedoorsites, as at 18 May 2026. Licence: CC BY 4.0.
Is ICT Fit out of Orange Door Sites late? Its planned finish is 31 Oct 2019, 10 months later than the 31 Dec 2018 first planned.
What is ICT Fit out of Orange Door Sites's latest rating? Its latest rating is Green (2019-20 Q2).