Family Safety Victoria online system of Tools for Risk Assessment and Management (TRAM) (DHHS) appears in 3 snapshots of the Victorian IT dashboard, from 2018-19 Q2 to 2018-19 Q4.
Its cost is $1.9m at 2018-19 Q4, against $1.7m at its baseline: +7%.
Its planned finish is 28 Jun 2019, 3 months later than the 29 Mar 2019 first planned.
Its latest rating is Green (2018-19 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Family Safety Victoria online system of Tools for Risk Assessment and Management (TRAM). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhhsfamilysafetyvictoriaonlinesystemoftoolsforriskassessmentandmanagementtram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Family Safety Victoria online system of Tools for Risk Assessment and Management (TRAM) cost? Its cost is $1.9m at 2018-19 Q4, against $1.7m at its baseline: +7%.
Is Family Safety Victoria online system of Tools for Risk Assessment and Management (TRAM) late? Its planned finish is 28 Jun 2019, 3 months later than the 29 Mar 2019 first planned.
What is Family Safety Victoria online system of Tools for Risk Assessment and Management (TRAM)'s latest rating? Its latest rating is Green (2018-19 Q4).