Divisional Telephony Program (DHHS) appears in 8 snapshots of the Victorian IT dashboard, from 2018-19 Q3 to 2020-21 Q2.
Its cost is $1.2m at 2020-21 Q2, against $2.3m at its baseline: -46%.
Its planned finish is 28 Feb 2021, 5 months later than the 1 Oct 2020 first planned.
Its latest rating is Green (2020-21 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Divisional Telephony Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhhsdivisionaltelephonyprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Divisional Telephony Program cost? Its cost is $1.2m at 2020-21 Q2, against $2.3m at its baseline: -46%.
Is Divisional Telephony Program late? Its planned finish is 28 Feb 2021, 5 months later than the 1 Oct 2020 first planned.
What is Divisional Telephony Program's latest rating? Its latest rating is Green (2020-21 Q2).